Yes. City of Parramatta’s Development Engineering Design Guidelines list dual occupancies and duplexes as development that needs on-site detention (Section 2, clause 1.1(c)). The 150 m² minor-works exclusion does not apply to dual occupancies (clause 1.2(e)). So the real questions are how big the tank is, where it goes, and how it legally discharges. Those are what hold up approvals.
OSD is a tank or storage area that holds stormwater during heavy rain and releases it slowly through a restricted outlet, called an orifice. The aim is to keep the peak flow leaving your site at or below what left it before development. A duplex replaces lawn with roof and driveway, so without OSD it sends much more water downstream, much faster.
OSD isn’t the same as a rainwater tank. A BASIX rainwater tank is there for reuse. An OSD tank has to be empty and ready for the next storm. Some designs combine the two, but Council will check that the detention volume sits separately from the reuse volume.
Parramatta LEP 2023 clause 6.5 (Stormwater management) is the head of power. The detailed rules sit in Council’s Development Engineering Design Guidelines, which set the sizing method by the former council area your lot falls in:
For residential development, OSD must be an underground tank, not an above-ground basin (clauses 3.1(a) and 3.1.2(a)). Council generally wants 1200 mm minimum internal depth, with 900 mm considered on tight sites, and 900 × 900 mm access grates. Habitable floors need 200 mm freeboard above the OSD top water level, and garages 100 mm.
This is where most duplex projects come unstuck. All development must drain by gravity (Section 1, clause 3.0). Up to 30 L/s can go to the kerb. Above that, you connect to Council’s pipe network, generally within 15 m. If the site falls away from the street, or is flat, the rules tighten:
On a site that falls away from the street, the OSD tank must drain by gravity through a registered easement over the downstream lot.
We recently handled a Parramatta Council request for information on a duplex where the dispute came down to exactly this: OSD location versus easement. The lesson is to sort out the discharge route before you lodge, not after Council asks.
For a Parramatta duplex, plan on OSD from day one. The tank is rarely what holds up approval. The discharge route is. Get that settled early and the rest of the approval goes far more smoothly.
Horizon Engineers designs stormwater and OSD systems for residential and commercial developments across Sydney. If your duplex has a tricky fall or an easement question, get in touch or see our stormwater design services.
Yes. Council’s Development Engineering Design Guidelines list dual occupancies and duplexes as development that needs on-site detention.
No. Council does not accept pump-out systems for OSD. Pumps are only allowed for basements and driveways.
You’ll need a drainage easement over the downstream property, with the owner’s written consent before you lodge the DA.
Only its dedicated airspace can partly offset the OSD volume, and only under the UPRCT Handbook 4th edition.
Disclaimer: This article is general in nature and based on City of Parramatta’s Development Engineering Design Guidelines. It is not advice for any particular site. Get site-specific engineering advice before relying on it.
Resources
News
Login
Address
Level 2, 96 Phillip St,
Parramatta, NSW 2150
Get in Touch
info@horizonengineers.com.au
(02) 9635 9890
News
Resources
Login