Does an Existing Building’s Roof Drainage Have to Comply with AS/NZS 3500.3?

Publish Date

23 November 2026

Line drawing of two roofs at the same level falling to a box gutter with sump, overflow and downpipe, and an eaves gutter with external downpipe, under AS/NZS 3500.3

Hussein Naji BE(Hons) MIEAust CPEng NPER – Director, Horizon Engineers

The short answer: not automatically. An existing roof drainage system generally only has to meet the standard that applied when it was built. But the moment someone does plumbing work on it, even replacing a gutter, that work has to comply with the current Plumbing Code. And strata law, council orders and insurers can push you to upgrade anyway.

Why this question keeps coming up

We get this question every time an older building floods during a storm. Owners corporations, facility managers, insurers and builders all ask a version of it:

  • “The building is 20 years old. Does it have to meet today’s AS/NZS 3500.3?”
  • “We’re only replacing the gutters like-for-like. Do they need to be upsized?”
  • “The audit says it’s non-compliant. Are we legally required to fix it?”

The answers sit across three documents that rarely get read together: the Building Code (NCC Volumes One and Two), the Plumbing Code (NCC Volume Three), and state legislation. This article walks through them using NSW, where most of our work is.

What the codes actually say

1. The Building Code is not retrospective. NCC Volume One (F1D3) and Volume Two (H2D2, H2D6) call up AS/NZS 3500.3 as the Deemed-to-Satisfy route for roof drainage. But the ABCB is clear that the NCC applies mainly to new buildings and new building work. It doesn’t generally reach back into an existing building unless that building is being altered, extended or changed in use.

2. The Plumbing Code is different. NCC Volume Three, the Plumbing Code of Australia (PCA), covers plumbing and drainage in new and existing buildings, and applies whenever plumbing work is carried out. Roof drainage is plumbing work. This is the part most people miss.

3. NSW law makes the PCA binding on the person doing the work. Under section 7 of the Plumbing and Drainage Act 2011 (NSW), the responsible person for plumbing and drainage work must make sure the work complies with the PCA. NSW Fair Trading is the regulator. The PCA’s Deemed-to-Satisfy path for roof drainage is AS/NZS 3500.3.

4. Which edition? AS/NZS 3500.3:2025 was published on 17 April 2025, with updated overflow and eaves gutter provisions. But NSW is still on NCC 2022 and doesn’t adopt NCC 2025 until 1 May 2027. So for NSW work today, comply with the edition the PCA currently references. Our advice: check your design against 2025 as well, because overflow provisions are where audits fail and the newer edition reflects current thinking.

Put simply: the building is judged against the code of its day. The work is judged against the code of today.

So when does an existing system have to comply?

The detail behind each branch:

SituationMust the current AS/NZS 3500.3 be met?Why
Nothing is being changed and the system works as builtNoAssessed against the code at the time of construction. The NCC isn’t retrospective
Gutters, downpipes, sumps or box gutters replaced or repairedYes, for the work doneThe PCA applies to plumbing work in existing buildings. The untouched parts don’t have to be upgraded
Alterations or additions add roof area or flowYes for the new work, and for any existing element that now takes the extra flowNew building work must comply with the NCC
Change of useDepends on the consent conditionsNSW upgrade-on-alteration powers focus on fire safety and structural capacity, not drainage, unless Council conditions it
Strata building where drainage has failed or leaksMust be repaired (s106, Strata Schemes Management Act 2015)The duty is to repair, not to upgrade. But the repair is plumbing work, so the repaired parts must meet the current PCA
Council issues a development control orderWhatever the order requiresOrders under Schedule 5 of the EP&A Act can require specific works
Insurer, lender or purchaser asks for complianceNot legally, but practically yesA contractual or commercial requirement, not a code one

The pattern: compliance is triggered by work, failure or an order, never by age alone.

Where people get it wrong

  1. “It’s existing, so it’s grandfathered forever.” Only while it’s working and nobody touches it. Once it fails, the repair duty kicks in, and once someone works on it, the current code applies to that work.
  2. “Like-for-like replacement is exempt.” Like-for-like may not need prior approval in some areas, but it still has to comply with the PCA. Replacing an undersized gutter with an identical undersized gutter is new non-compliant work.
  3. “Compliance is about gutter size.” In our experience it’s mostly about overflow. Gutters and downpipes are often close enough. Overflow provisions are where buildings fail.
  4. “The audit says non-compliant, so we’re in breach.” A compliance assessment against the current standard tells you the risk, not necessarily a legal breach. It’s still the best evidence you have that you’ve met your duty of care once you know.

What we see on real assessments

Horizon carries out roof drainage compliance assessments on existing commercial and industrial buildings, mostly from roof condition audits commissioned after a leak or flood. The same pattern shows up again and again:

  • Overflow is the main failure. Overflow provisions are undersized more often than downpipes. Occasionally a roof section has no overflow at all.
  • Downpipes are often marginally undersized against the current standard: close, but not compliant.
  • The fix is usually targeted, not a redesign. Adding sumps, downpipes or overflow outlets at the over-capacity locations generally brings the system into line at a fraction of the cost of re-engineering the whole roof.
  • Overflow discharge needs checking. Confirm overflows discharge to atmosphere on their own path, not back into the system that’s already full.

The practical takeaway for owners: you may not be required to upgrade, but a targeted fix found by a proper assessment is far cheaper than the next flood claim.

So, does an existing building’s roof drainage have to comply with AS/NZS 3500.3?

No, not by age alone. An existing system is judged against the standard it was built to. But any new plumbing work on it must comply with the current Plumbing Code and AS/NZS 3500.3, and owners must keep it working.

Need an assessment?

Horizon Engineers carries out roof drainage compliance assessments on existing commercial, industrial and strata buildings across Sydney. We check gutters, box gutters, sumps, downpipes and overflows against AS/NZS 3500.3 and tell you what actually needs fixing. Contact us for a fee proposal.


Disclaimer: This article is general in nature and focused on NSW. It is not advice for any particular site. Requirements vary by state, consent conditions and strata by-laws. Get site-specific engineering and legal advice before relying on it.

Hussein Naji, Director, Horizon Engineers